Create a Gantt chart for a mobile app development project
About the framework
The sample starts on March 1, 2026, with User Research and Competitive Analysis. Requirements Doc follows research. All three discovery tasks are marked done, and Wireframes is marked active. UI Design System and Prototype and Testing complete the design sequence.
Development begins with Core Features, followed by parallel API Integration and Push Notifications tasks. QA and Bug Fixes follows API Integration; App Store Submission and Marketing Launch both follow QA. The chart has 12 tasks across four sections, with no explicit QA dependency on Push Notifications.
Use the status markers as sample annotations, not current project progress. Replace dates, durations, and task names, then review how parallel branches join. If marketing must wait for store approval, add that gate rather than relying on the existing submission task.
What's included
Mobile App Development Gantt Chart
✦ Free preview · Sign in to use
Explore more
Frequently asked questions
No. It is a filled mobile app development example with dates, durations, dependencies, and selected status markers.
User Research, Competitive Analysis, and Requirements Doc are marked done. Wireframes is the only task marked active.
No approval task is included. Marketing Launch and App Store Submission both follow QA and Bug Fixes, so add an approval dependency if needed.
Free to start. No credit card required.