Create a simple Gantt chart example for a small project
About the framework
Planning contains Requirements gathering and Stakeholder approval. Design adds Wireframes, Visual mockups, and a Design review milestone. Development includes Frontend build, Backend integration, Testing, and a Launch milestone. There are seven duration-based tasks and two zero-duration milestones.
Frontend and backend work both follow Visual mockups, so they can overlap. Testing follows Backend integration, and Launch follows Testing. The sample durations span 43 calendar days from the March 1, 2025 start, a little over six weeks; no weekend exclusions are specified.
This example is useful for tracing one task into the next and comparing overlapping work. For a real redesign, replace the estimates and make design approval and completion of both build tasks explicit prerequisites where your process requires them.
What's included
Simple Gantt Chart Example
✦ Free preview · Sign in to use
Explore more
Frequently asked questions
The chart has seven tasks with durations and two zero-duration milestones: Design review and Launch.
Frontend build and Backend integration both start after Visual mockups. The frontend task lasts 10 sample days and the backend task 14.
The linked sample durations total 43 calendar days, slightly more than six weeks. The chart does not exclude weekends or holidays.