Mobile App Development Gantt Chart

Gantt chartEngineering · Mobile App PlanningMade from one prompt
Read-only preview

The prompt

Create a Gantt chart for a mobile app development project

Make your own version

About the framework

Plan a mobile app from discovery through launch

The sample starts on March 1, 2026, with User Research and Competitive Analysis. Requirements Doc follows research. All three discovery tasks are marked done, and Wireframes is marked active. UI Design System and Prototype and Testing complete the design sequence.

Development begins with Core Features, followed by parallel API Integration and Push Notifications tasks. QA and Bug Fixes follows API Integration; App Store Submission and Marketing Launch both follow QA. The chart has 12 tasks across four sections, with no explicit QA dependency on Push Notifications.

Use the status markers as sample annotations, not current project progress. Replace dates, durations, and task names, then review how parallel branches join. If marketing must wait for store approval, add that gate rather than relying on the existing submission task.

What's included

What you get

  • Twelve tasks across Discovery, Design, Development, and Launch
  • Three discovery tasks marked done and Wireframes marked active
  • Parallel API integration and push-notification tasks
  • App-store submission and marketing launch following QA
Gantt chart

Mobile App Development Gantt Chart

ganttproject managementtimelinesprint

✦ Free preview · Sign in to use

Frequently asked questions

Common questions

Is this a blank project schedule?

No. It is a filled mobile app development example with dates, durations, dependencies, and selected status markers.

Which tasks are marked complete?

User Research, Competitive Analysis, and Requirements Doc are marked done. Wireframes is the only task marked active.

Does marketing wait for app-store approval?

No approval task is included. Marketing Launch and App Store Submission both follow QA and Bug Fixes, so add an approval dependency if needed.