Create a Gantt chart for a commercial building construction project spanning site prep through final inspection
About the framework
Six sections organize 12 tasks: Site Prep, Foundation, Structure, MEP, Finishing, and Inspection. Land Survey & Permits starts on January 5, 2026. Later work includes Footings & Concrete, Steel Framework, Electrical & Plumbing, HVAC Installation, Interior Build-Out, and Final Handover.
The plan allows overlap after Steel Framework: Exterior Walls & Roof and Electrical & Plumbing both follow it. Finishing follows the exterior work, while HVAC follows electrical and plumbing. The inspection path depends on Fixtures & Painting; no explicit link requires HVAC completion before inspection.
Treat the dates and durations as planning examples. Replace them with project estimates and review all prerequisites, especially where parallel trades converge. The chart contains no named contractors, resource limits, holiday calendar, or inspection criteria.
What's included
Construction Project Gantt Chart
✦ Free preview · Sign in to use
Explore more
Frequently asked questions
There are six: Site Prep, Foundation, Structure, MEP, Finishing, and Inspection, with two tasks in each section.
The displayed Code Compliance Review depends only on Fixtures & Painting. Add the required MEP completion dependencies for your project.
The source specifies day durations but no weekend or holiday exclusions. Supply your project calendar when adapting the schedule.